Mini-Holland (Go Cycle) – March 2019 update

Following our look at what should be delivered during 2019 on Kingston’s GoCycle schemes, how is progress going?

Wheatfield Way

The Wheatfield Way scheme started towards the end of 2017 and it is finally approaching its conclusion with works around Orchard Road junction the last substantial area to finish. The Wheatfield Way scheme will provide a new route through Kingston town centre although areas of shared use around junctions will unfortunately affect the usability of the route. A number of items remain to complete the whole route with signs and paint markings still to be added to clearly show that it is a cycle route. Works outside Pryzm to finish that part of the route (started but not finished at the end of 2017) are due to take place in the next couple of months.

20mph signs have recently been added to parts of the Wheatfield Way route (replacing the previous 30mph limit) and we are hoping that the 20mph limit will therefore soon be in force.

IMG_20190304_154950

New 2-way cycle track on Wheatfield Way between Orchard Road and Brook Street crossing

Eventually Wheatfield Way will form part of a continuous cycle route all the way from Tolworth Broadway to Kingston station (a distance of about 3 miles!).

Kingston Vale

The largest amount of visible activity so far in 2019 on the Mini-Holland programme has been on the Kingston Vale route between Galsworthy Road and Derwent Avenue. A large amount of one-way segregated cycle track has been built so far with work on the bus boarders (see below) almost complete too. The outstanding work on this section is mainly the installation of a separator to provide a barrier between the road and the cycle lane where the existing kerb did not need to be moved.

Rediweld Milestone

The Rediweld Milestone cycle separator which should keep motor vehicles away from the cycle lane on Kingston Vale

We were pleased to hear from the Council that they will be trialling a new type of separator which will provide better segregation for cyclists from the road. This separator is called the Rediweld ‘Milestone’ (see photo). This Milestone separator provides a more substantial barrier between the road and the cycle lane than the ‘orcas‘ that were originally proposed. One of the problems with orcas is that vehicles could still cross the cycle lane through the gaps between each orca. This will be much more difficult to do with the Milestone separator which will be laid in a continuous line (except at junctions and crossings). All of these types of separators bolt down into the road surface. Therefore, once the preparations are complete, they can be installed very quickly. We are looking forward to them being installed! The upgraded cycle route between Galsworthy Road and Derwent Avenue should be completed by the end of Spring 2019.

Whilst we are pleased with what is planned in the areas which are segregated, we are concerned about the designs of the ‘bus boarders’ that have been installed so far on the Kingston Vale route. These bus boarders allow people on bikes to avoid rejoining the road around bus stops and therefore are essential to provide a continuous, safe and attractive route to people on bikes where space does not allow a bus stop bypass. However, the bus boarder design that has been implemented on Kingston Hill (see photo) does not clearly show where people waiting for a bus should wait and where people on bikes should cycle. We would have preferred if the established and successful design on Portsmouth Road had been used. Alternatively, we think other areas have implemented better designs too (for example, Waltham Forest and Enfield). We have been unsuccessful in getting the Council to change the Kingston Vale bus boarders but we understand that they are subject to a trial and will be monitored with changes therefore possible in the future. If you have any concerns about the bus boarder design on Kingston Vale then do let the Council know.

IMG_20190310_164226

Bus boarder on Kingston Hill. The bus stop flag will be moved to the kerb when finished.

Works will continue on the rest of the route (including finishing Manorgate roundabout) during the rest of the year and into 2020.

Penrhyn Road

Construction on the Penrhyn Road scheme has started and is already mostly complete between College Roundabout and Denmark Road. Work continues from Denmark Road towards the main Kingston University campus as a 2-way cycle track is built from the end of the Wheatfield Way scheme to Surbiton Road, connecting into Surbiton Crescent allowing safer cycling between Surbiton and Kingston.

Kingston Station

‘Snagging’ works continue around the main station plaza with the cycle route to Fife Road improved, drainage issues being worked on underneath the railway bridge and the crossing outside the Rotunda upgraded to a ‘toucan’ allowing people on bikes to use this crossing.

The next major milestone on this project will be the installation of the replacement pedestrian and cycle bridge over Kingsgate Road which will provide an improved link between Kingston Station and Skerne Road. Installation is due to take place over 23/24 March with works then continuing to build the paths either side of the bridge.

New Malden to Raynes Park

Although not very visible, work continues on the off-road New Malden to Raynes Park route. Most of the separate pedestrian and cycle paths have now been prepared with work getting ready for the installation of steps and a ramp to connect the route with Alric Avenue and Dukes Avenue.

IMG_20190224_155445

New Malden to Raynes Park separate cycle and pedestrian paths. Segregation is to be added in the foreground once the steps have been added to the bridge joining Alric and Dukes Avenues

Work will continue on the route over the coming months and it should be ready to open by early Summer 2019.

Links to further information from Kingston council:

Advertisements

One thought on “Mini-Holland (Go Cycle) – March 2019 update

Leave a reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s

This site uses Akismet to reduce spam. Learn how your comment data is processed.